Holiday sprint planning: plan for the team you'll actually have
Holiday sprint planning in five steps: count person-days, scale your forecast, protect scarce skills and keep a buffer, with the numbers behind each step.

Holiday sprint planning starts with the calendar
Holiday sprint planning goes wrong in a quiet way. The backlog looks normal, the team commits to its usual velocity, and then half the people vanish for a week. By the review, a big part of the sprint is rolling over into January.
The fix is not a new framework. It is doing the capacity math before anyone picks a story. This post walks through a simple method you can run in your next Sprint Planning, with the numbers to back it.
What the data says about holiday availability
Last December, Dayforce published a survey run by The Harris Poll. It asked 2,567 full-time employees in the US, Canada and the UK about their holiday plans. Fieldwork ran from 20 to 25 November 2025.
- 95% said they get or plan to take time off over the holidays.
- Only 42% said they unplug from work completely during that time off.
- 67% said they feel pressure from their employer to be available while off.
This is vendor research from an HR software company, so treat it as a signal, not a law. But the signal is clear. Almost everyone takes time off, and many of them half work while away. Neither of those is capacity you can plan on.
Step 1: Count person-days, not people
A team of six is not "six people" in a holiday sprint. It is a number of working days.
Open a shared calendar and go person by person. Mark public holidays, planned leave and half days. Stefan Wolpers puts it simply on the Scrum.org blog: "Take five minutes during the Sprint Planning and create a shared understanding of who will be available when."
If your team plans in hours, go one level finer. We covered why in Your sprint runs in hours. Why does Jira plan it in days?.
Step 2: Scale your forecast to the days you have
Mike Cohn's Mountain Goat Software gives a plain formula:
Predicted velocity = average velocity × (planned working days ÷ average working days)
The worked example: a six-person team on two-week sprints averages 55 working days and 40 points per sprint. One person is out for the whole sprint. The other five each lose one day to a national holiday. That is 15 days lost, so 45 days remain.
40 × (45 ÷ 55) = 32.72. Plan for 32 or 33 points, not 40.

The same idea works with hours. If you size work with story points, keep your normal scale. Don't shrink points to fit the holiday. Shrink the commitment. Our guide on sizing user stories with story points explains why the scale should stay stable.
Step 3: Check the skill that has no backup
Proportional math assumes everyone can do everyone's work. Real teams rarely work that way.
The same article's second example: a team has two database specialists and one is away. That is a 17% cut in total people but a 50% cut in database work. Its advice is to reduce the forecast by the largest impact, not to add up every absence.
So before you commit, ask one question. Whose absence blocks the most work this sprint? Plan around that person's calendar first.
Step 4: Don't count the laptop on the beach
When only 42% of people fully unplug, it is tempting to assume "they'll check in." Don't. Work done on leave is unreliable, hard to review and often redone later.
Plan as if people on leave are fully off. If they choose to help, it becomes a bonus. It should never be the reason the Sprint Goal is reachable.
Step 5: Leave a buffer and a pull list
On the Atlassian Community, Bill Sheboy notes that "sometimes scrum teams leave buffer capacity" for uncertainty. He pairs that with keeping ready work you can pull in if time frees up.
That fits holiday sprints well. Commit below your scaled forecast. Keep two or three small, ready items at the top of the backlog. If the week goes better than expected, pull them in. If not, nothing rolls over.
One warning on tooling. In the same forum, Nic Brough points out that editing Jira's capacity settings for each sprint is "painful" and can throw off your reporting. Keep the math simple and visible instead.
Seeing holiday capacity before you commit
Steps 1 and 3 are where most teams lose time. Someone builds a spreadsheet of leave, someone else forgets a half day, and the numbers drift from what Jira shows.
LazyScrum runs Sprint Planning live on top of Jira and calculates each person's real capacity. You see everyone's load on a 30-minute timeline, so the person with no backup and the half day before New Year show up before you commit, not after. If you want to try it on your holiday sprint, there is a 7-day free trial at lazyscrum.com.
Your turn
How does your team handle the last sprint of the year? Do you shorten it, keep the rhythm at lower capacity, or plan a quieter sprint on purpose? Tell us what worked.